Burns Cooley Dennis, Inc. (BCD) provided geotechnical consulting services for bridge foundations and pavements and construction materials testing, inspection and engineering services for Mississippi Department of Transportation’s (MDOT) State Route 9 Design-Build Project in Pontotoc County, Mississippi. The project consisted of approximately 9.5 miles of new four-lane roadway from U.S. 278/S.R. 6 near Pontotoc to U.S. 78 at Sherman. The project included eight at-grade intersections, an interchange at Endville Road and grade separations at Dozier Hill Road and Eads Creek Road. Construction included 7 million cubic yards of earthwork, approximately 170,000 tons of asphalt pavement, and ten bridges.
Geotechnical services included preparation of geotechnical reports including pile design and verification using dynamic pile testing, drilled shaft design and verification using Osterberg load testing, stability analysis of embankment slopes and cut slopes, and settlement analyses of embankments. Materials testing services included daily field and laboratory testing for embankment soils, design, soils, stabilized subgrade soils, cement stabilized subbase materials, granular base materials, shoulder materials, hot-mix asphalt pavements and concrete structures. BCD also provided QC construction inspection services during deep foundation installation, bridge construction, embankment/roadway construction, hot-mix asphalt placement, pavement striping, and roadway signage and traffic control.
Project Details
DATE
September 2012
CLIENT
MS Dept. of Transportation
PROJECT TYPE
Bridges and Pavements
AWARDS
ACEC-MS 2012 EEA Honor Award